The following analysis estimates the cost to build a town hall, 1 story using US National Average costs from 2013 RSMeans cost data. Costs are derived from a building model that assumes basic components, using union labor for
a 11000 square foot building.
Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a town hall, 1 story in a specific city or metropolitan area, go to our index of town hall, 1 story models by state .
NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on Construction Estimating Software
Try Free For 30 Days
Town Hall, 1 Story Construction Cost Assumptions |
Location: |
US National Average
|
Stories: |
1
|
Story Height (L.F.): |
12.00
|
Floor Area (S.F.): |
11000
|
Basement Included: |
No
|
Data Release: |
Year 2013
|
|
Town Hall, 1 Story Square Foot Cost Assuming Brick Veneer / Wood Frame
Cost Estimate (Union Labor) |
% of Total |
Cost Per SF |
Cost |
Total |
|
$93.91 |
$1,033,000 |
Contractor Fees (GC,Overhead,Profit) |
25% |
$23.48 |
$258,300 |
Architectural Fees |
9% |
$10.56 |
$116,200 |
Total Building Cost |
$127.95 |
$1,407,500 |
Cost Estimate (Open Shop) |
% of Total |
Cost Per SF |
Cost |
Total |
|
$86.18 |
$948,000 |
Contractor Fees (GC,Overhead,Profit) |
25% |
$21.55 |
$237,000 |
Architectural Fees |
9% |
$9.70 |
$106,700 |
Total Building Cost |
$117.42 |
$1,291,700 |
OTHER OPTIONS:
Town Hall, 1 Story Square Foot Cost Assuming E.I.F.S. / Wood Frame
Town Hall, 1 Story Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Steel Joists
Town Hall, 1 Story Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Wood Joists
Town Hall, 1 Story Square Foot Cost Assuming Stone with Concrete Block Back-up / Steel Joists
Town Hall, 1 Story Square Foot Cost Assuming Stone with Concrete Block Back-up / Wood Joists