The following analysis estimates the cost to build a courthouse, 2-3 story using US National Average costs from 2013 RSMeans cost data. Costs are derived from a building model that assumes basic components, using union labor
for a 60000 square foot building.
Scope differences and market conditions can cause costs to vary significantly. To see an estimate of the costs to build a courthouse, 2-3 story in a specific city or metropolitan area, go to our index of courthouse, 2-3 story models by state .
NOTE: This cost estimate uses 2013 RSMeans data. A more accurate estimate using current RSMeans cost data is available on Construction Estimating Software
Try Free For 30 Days
Courthouse, 2-3 Story Construction Cost Assumptions |
Location: |
US National Average
|
Stories: |
3
|
Story Height (L.F.): |
12.00
|
Floor Area (S.F.): |
60000
|
Basement Included: |
No
|
Data Release: |
Year 2013
|
|
Courthouse, 2-3 Story Square Foot Cost Assuming Face Brick with Concrete Block Back-up / R/Conc. Frame
Cost Estimate (Union Labor) |
% of Total |
Cost Per SF |
Cost |
Total |
|
$153.26 |
$9,195,500 |
Contractor Fees (GC,Overhead,Profit) |
25% |
$38.31 |
$2,298,900 |
Architectural Fees |
7% |
$13.41 |
$804,600 |
Total Building Cost |
$204.98 |
$12,299,000 |
Cost Estimate (Open Shop) |
% of Total |
Cost Per SF |
Cost |
Total |
|
$140.78 |
$8,447,000 |
Contractor Fees (GC,Overhead,Profit) |
25% |
$35.20 |
$2,111,800 |
Architectural Fees |
7% |
$12.32 |
$739,100 |
Total Building Cost |
$188.30 |
$11,297,900 |
OTHER OPTIONS:
Courthouse, 2-3 Story Square Foot Cost Assuming Face Brick with Concrete Block Back-up / Steel Frame
Courthouse, 2-3 Story Square Foot Cost Assuming Limestone with Concrete Block Back-up / R/Conc. Frame
Courthouse, 2-3 Story Square Foot Cost Assuming Limestone with Concrete Block Back-up / Steel Frame
Courthouse, 2-3 Story Square Foot Cost Assuming Stone with Concrete Block Back-up / R/Conc. Frame
Courthouse, 2-3 Story Square Foot Cost Assuming Stone with Concrete Block Back-up / Steel Frame