Construction cost overruns are serious risks that can send ripples throughout an organization’s budgets and operations. In an ideal world these hazards would be avoided, but leaders don’t always have the robust estimating data required to plan and budget with confidence. To make the most of their available resources and leverage accurate budgets and forecast to request future funding, decision-makers need up-to-date, locally relevant cost estimating data to help minimize uncertainty and error.

Causes and challenges

Those involved in planning and budgeting know that cost overruns are not typically the result of any one mistake in the construction process, but rather the outcome of many minor mishaps in the initial stages of the lifecycle. As an article in the Houston Chronicle noted, reasons for overruns can include uncoordinated schedules, late-stage changes in project scope or unrealistic designs that end up costing contractors more than expected.1 Or, the problem stems from the estimates themselves.

“A common reason for cost overruns is the inaccuracy of cost estimates.”

Bert Markgraf

“A common reason for cost overruns is the inaccuracy of cost estimates,” writes small business columnist Bert Markgraf. “When the bids for subcontracts or the actual costs come in, they are often higher than anticipated. Such cost overruns are due either to incorrect estimates or to changed conditions in the marketplace.1”

Construction projects, whether new capital builds or minor renovations, start with planning and often include design – the beginning stages of the building lifecycle. Accuracy in cost estimating can combat risk in each of these areas, allowing those involved to focus on other key areas of the process. Accurate cost estimating data can help drive decisions within the boundaries set by budgets. Precise cost estimating data can also improve and accelerate the planning process, reducing the errors and waste that result in overruns.

Real-world concerns

The battle with cost overruns is a universal one.

The cost of the expansion of the Jacob K. Javits Center rose to approximately a half-billion more than announcements made in 2016. The 1.2 million square foot addition was originally projected to cost about $1 billion, and state officials put the price tag at $1.55 billion. The original announced projection did not include “soft costs” for the project and came before any design details had been decided, according to those interviewed for the article.2

Likewise, a Panama Canal expansion project is looking at up to $2 billion in additional cost overruns. Original bids put the project at $3.2 billion, but the Grupo Unidos por el Canal (GUPC) is claiming up to $5.4 billion more, tripling the final cost of the canal. The claims are currently undergoing litigation and could be unresolved for years.3

 

Smaller profile projects are not immune to cost overruns, either. A courtroom-police administration building project in Troy, New York saw a budget increase of $1 million, according to the local paper.4 In this project, the overrun issues arose from the police administration building project coming in over budget. But at this point, the city has no choice but to move ahead with the project.

With improved estimating resources that reflect up-to-date cost data, decision-makers can avoid these setbacks and ensure a seamless construction lifecycle.

Data proves invaluable

RSMeans Data from Gordian is the most trusted source of construction cost data in North America, and includes costs for more than 970 locations in North America. Tracking regional factors in this way allows those in the construction industry to maximize accuracy in planning, estimating and budgeting and compare costs across different localities. RSMeans Data also includes labor, material, equipment and productivity rates, providing the most up-to-date and comprehensive construction cost information. This allows estimators, planners, contractors, facility managers and owners to understand the full cost of a project to help eliminate pricing surprises as the project progresses. Those involved in the beginning stages of the project must fulfill many responsibilities to minimize the risk of a cost overrun, but with accurate, regionally aligned RSMeans Data, their efforts will be kept on track throughout the rest of the construction process.

 

Test drive North America's leading construction cost database. Take an interactive product tour of RSMeans Data Online.


1http://smallbusiness.chron.com/effective-project-management-small-business-organization-41274.html
2http://www.crainsnewyork.com/article/20170202/REAL_ESTATE/170209973/price-tag-of-javits-center-expansion-jumps-by-half-billion-dollars
3http://www.maritime-executive.com/article/panama-canal-cost-overrun-claim-rises-2-billion
4http://www.timesunion.com/local/article/Troy-officials-getting-updates-on-several-projects-10852568.php