Back to: Home > Links > RSMeans Estimating Handbook Excerpt
Excerpted from RSMeans Estimating Handbook
Helpful Estimating Tips
Division 1 - General Requirements
Division 2 - Site Work
Division 3 - Concrete
Division 4 - Masonry
Division 5 - Metals
Division 6 - Wood & Plastics
Division 7 - Thermal & Moisture Protection
Division 8 - Doors and Windows
Division 9 - Finishes
Division 10 - Specialties
Division 11 - Equipment
Division 12 - Furnishings
Division 13 - Special Construction
Division 14 - Conveying Systems
Division 15 - Mechanical
Division 16 - Electrical
Division 1 - General Requirements
In figuring general requirements, do not include the salaries of
the project managers or of any other personnel who are not
directly site-related. Their wages are included in the "Main
Office" expenses.
Always allow for cleanup in the estimate. No matter how clean a
subcontractor leaves an area, it is almost always necessary to
clean the area again.
In locations where snow is likely, allow for the expense of
snowplowing if the project begins, ends, or works through the
winter season. Another consideration is melting snow, which will
inevitably end up in trenches, pits, or other low areas.
Consequently, pumping costs should also be carried.
Always visit a proposed site. Do not rely on someone else's
judgment unless statements in the contract require it.
Check for:
Site Access--Can loaded trucks move into and out of the site
easily? Is the site in/near a residential area? Are there
height/weight restrictions?
How far away are the utilities that can be hooked into for
temporary power?
Site Drainage--Is the area marshy? Will there be water problems
when it rains?
Do any utilities need to be relocated?
Will any adjacent structures be affected?
If any of these items apply to the project, the associated costs
must be estimated and included in the project bid/estimate.
The cost for installing temporary utilities, especially
lighting, may be included in the specifications for the
respective trades. Check this out to avoid adding an unnecessary
cost to the estimate.
Pit Excavation
When figuring the slope areas of pit excavation, remember that
the slope areas usually form a right triangle when viewed as a
section. Since the area of two right triangles equals the area
of one rectangle with equal base and height dimensions, the
volume of the slope area will equal the depth of the pit (the
height) times the cut back distance of the slope (the base)
times 1/2 the perimeter of the pit.
Cut and Fill
If a project has a large quantity of cut or fill, consider
inquiring whether the site grade can be raised or lowered to
economize the earthwork portion of the estimate.
If the project requires a large quantity of fill, consider
creating a borrow pit on the site. This can lower the estimate
significantly, as the cost for suitable fill material can be
quite high in some areas of the country. The borrow pit can also
be helpful as a receptacle for on-site spoil or other excavated
materials, in this case saving dump charges.
It is very important to keep in mind while estimating earthwork
the location and availability of dump sites for spoil.
Unexpectedly large costs can accrue if the only site open to
receive spoil is quite a distance away.
Clearing and Grubbing
Often one of the most expensive parts of clearing and grubbing
is the disposal of tree stumps. It is a good idea to know how
and where this task can be carried out before completing the
estimate.
Site Access
One of the most common mistakes made in site work estimating
involves site access. Estimators should visit the site not only
to review site conditions, but to trace the route that the
general or subcontractors' equipment will take to get to the
site. If the equipment that is to be used on this project cannot
get to the site, the estimate may be completely inaccurate.
Pavings
When estimating paving, keep in mind the overall project
schedule. Although it is common to wait until the end of the
project before paving, consider what time of year the project is
scheduled for completion. In colder climates, many concrete
plants close for the season in late November and are thus very
busy just before then. The supply or availability may be
limited, and the prices may be higher.
Quick Quantity for Asphaltic Concrete Paving
A quick rule of thumb for Asphaltic Concrete is that for each
inch of pavement thickness, 1 square yard = 110 lbs.
Sewerage and Drainage
One should not automatically assume that the sewerage and
drainage lines will go in at the early stages of the project. It
may appear to make sense from a scheduling standpoint, but the
inconvenience of having the site divided in half, with open
trenches, loose pipe, and restricted access may ultimately cost
more in lost time.
Subsurface Investigations
Many companies, eager to get started on their projects,
shortchange the site investigation process. For the relatively
short time and small amount of money involved, it is not a good
idea to skimp on this important item. The untimely discovery of
even one subsurface "abnormality" can be a painful lesson. An
example is finding that the site was unknowingly used "way back
when" as a spoils site for the rest of the industrial park and
that there are ten feet of bad soils to excavate from under the
stiff clay cap you assumed you would build on. Investigate the
site thoroughly!
Miscellaneous Hauling Time and Distance Rule
30 MPH = 44 Feet per Second
Concrete Block-outs
When estimating quantities of concrete for floor slabs or walls,
do not bother to deduct small areas (two square feet or so)
unless there are a large number of these areas, as this can take
up more estimating time than the areas are worth. Also remember
that you will be adding approximately 3% to the total volume for
waste, thereby making these small areas even less significant.
Reinforcing Steel Adds
When estimating the amount of reinforcing steel, either bar or
mesh, if no lap specifications are given, add 10% to your
quantities for lapping, splices, and waste.
Check All Plans
It cannot be stressed enough that all plans for concrete must be
checked. Concrete has been known to show up in all sections of
construction drawings in various forms and uses (e.g., equipment
pads location only on mechanical or electrical drawings,
grouting requirements on steel drawings, etc.). Assuming all
concrete requirements are indicated on the structural and
architectural drawings can be a costly error.
Cold Weather Pouring of Footings
When placing concrete in cold weather, it may not always be
necessary to use heating devices to keep concrete warm while it
cures. In many cases, insulating blankets and straw are all that
are needed. Each situation must be evaluated individually, a
worthwhile exercise in view of the considerable expense that can
be saved.
Concrete Placement--Direct Chute
When estimating the placement of concrete by direct chute, the
forms available generally determine the volume of concrete
placed per hour. The more you have available, the more concrete
can be placed in the course of a day.
Form Uses
When estimating the number of forms and reuses for a job,
remember to have enough forms on hand to keep the forming
crew(s) busy while the previously poured concrete sets and
starts to cure.
Concrete Placement--Bucket, Pump, or Conveyor
When placing concrete by methods involving a bucket and crane,
pumping system, conveyor belt system or other mechanical system,
set up enough forms to keep the above systems productive for the
entire day. Usually the cost for the use of the equipment for a
full day will be charged to you even if you only use it for part
of a day.
Sequencing the Pour
During the estimating phase of the project, whatever method or
sequence you envision for placing concrete, document it
thoroughly. The main reasons for complete documentation are that
it lets the field know how you arrived at the estimated cost,
manpower, and equipment costs; and what methods they should use
or try to out-do (in terms of cost effectiveness). Another
reason for detailed documentation is that during the documenting
process, it may become evident that you cannot place the
concrete as you planned or that you can do it differently, more
efficiently, or at less cost.
Testing Concrete
When estimating the amount of concrete compression testing that
will be necessary for a project, figure on a minimum of one test
per pour on smaller pours and a minimum of one test for each
fifty yards of concrete placed. Each test should consist of
taking a set of three cylinders minimum.
Finishing Concrete
Rule of thumb for finishing concrete: Allow 1 man for each 1,000
S.F. of slab.
Drilling Anchor Bolts
Consider drilling anchor bolts into the concrete to save time,
manpower, and materials on layout and templates during the pour.
Masonry Wall Block-outs
When estimating quantities for masonry walls, do not deduct
areas less than two square feet in area. They will more than
likely use cut whole block and should be figured as such.
Masonry Accessories
Remember to include miscellaneous items in your masonry
estimate; they tend to get overlooked. These items include but
are not limited to flashing, reinforcing, anchors, wall ties,
inserts, bearing plates, lintels, support angles and channels,
allowance for joist pockets, waterproofing, cleanup, final
cleaning and pointing, steam cleaning, acid or power wash, color
for mortar, and control joints. For a more detailed list, see
the checklist located at the end of this chapter.
Site Cleanup
If the plan at the time of the estimate is to erect masonry
walls after concrete slabs have been poured, keep in mind that
the masonry contractor will be responsible for cleaning the
dropped mortar off the concrete slab. Allow for this cleanup.
Bracing
One commonly overlooked item in masonry estimating is an
allowance for bracing walls, Until the structural system is tied
into the masonry wall systems, the wall can be blown over
relatively easily.
Panelization
Plan ahead. Could your next project, which is not scheduled to
start until later, be built with pre-assembled panels? If you
have the manpower available today, it might be economical to
have the contractor pre-build the walls in panelized sections in
their yard, then deliver and quickly erect them at the site.
This could save quite a bit of time on the project.
Special Brick
When a project calls for special brick such as utility sized for
glazed, remember that these (especially glazed) more than likely
will be special order. The order an manufacture time can be
surprisingly long. Paying a premium or extra charges may be the
only way to ensure faster "on-time" delivery.
Split Face Block
Split face block will take longer than common block to set. This
is due to the fact that these blocks have a somewhat irregular
depth dimension (on account of the splitting process). They do
not look "right" if set by lining up the squared corners.
Adjustments must be made to have them line up properly.
Bricklaying Productivity
The national average productivity for laying brick ranges from
400 bricks per day (considered "low productivity") to 600 bricks
per day (considered "high productivity").
Economy in Bricklaying
The following guidelines may be used to obtain economy in
bricklaying:
Plan to have adequate supervision. Be sure bricklayers are
always supplied with materials, so there is no waiting. Place
the best bricklayers at corners and openings.
Use only screened sand for mortar. Otherwise, labor time will be
wasted picking out pebbles. Use seamless metal tubs for mortar,
as they do not leak or catch trowel. Locate stack and mortar for
easy wheeling.
Have brick delivered for stacking. This makes for faster
handling, reduces chipping and breakage, and requires less
storage space. Many dealers will deliver select common brick in
2' x 3' x 4' pallets, or face brick packaged. This affords quick
handling with a crane or forklift, and easy tonging in units of
ten, which reduces waste.
Use wider brick for one wythe wall construction. Keep
scaffolding away from wall to allow mortar to fall clean and not
stain wall.
On large jobs, develop specialized crews for each type of
masonry unit.
Consider designing for prefabricated panel construction on
high-rise projects.
Avoid excessive corners or openings. Each opening adds about 50%
to the labor cost for the area of the opening.
Bolting stone panels and using window frames as stops reduces
labor costs and speeds up erection.
Anti-graffiti Products
If not specified, consider adding as an option the application
of one of the various anti-graffiti or vandalism products. These
coatings are roller, brush or spray-applied to close the pores
of the brick, thereby preventing permanent damage. Remember that
graffiti and vandalism are present in all cities and towns, not
just the major metropolitan areas.
Plates and Connections
When estimating the total tonnage of structural steel, add 10%
to the total weight to allow for plates, connections, an waste,
as a rule of thumb.
Shop-Applied Finish Paint
When the specifications call for the finish coat of paint to be
applied prior to installation, allow considerable time for
touching up the paint. Every time you lift, move, weld, bolt or
alter the position of a piece of steel, you will need to touch
up the finish.
Joist Bridging
It generally costs less to install joist systems that can
utilize horizontal bridging (as opposed to cross or other types
of bridging).
Items Listed
Note that on construction documents not all rough carpentry
items are listed or noted. Protective treads, inserts, and rails
are examples of necessary but not listed items that the
contractor must provide.
Item Search
The search for carpentry items must include roof sections, wall
sections, and all detail drawings.
Temporary Construction
Temporary construction should be included in Division 1, though
it may sometimes be listed in Division 6. Double check to assure
yourself that you are not double-pricing these items.
Treated Lumber
Treated lumber should always be used when the lumber will come
in direct contact with concrete, masonry, or the earth.
Bridging
Even when bridging is not shown on joist drawings, always
include it, as it helps to distribute concentrated loads to the
adjacent joists.
Blocking
One of the most overlooked areas of wood blocking is at roof
edges. Almost always, a built-up roof or membrane roof system
will require some sort of blocking and/or cant strip system.
Millwork
When budgeting millwork, a rule of thumb is that the total cost
of millwork items will be two to three times the cost of the
materials required. Do not overlook adding protection to all
millwork, especially if the work is by others.
Pricing
Do not rely on yesterday's material quotes. Due to current and
predicted shortages of lumber and the resultant fluctuations in
the market, caution is warranted.
Estimating Help
Short of time? Many lumber yards retain competent estimators who
will provide material lists/estimates from your plans for little
or no cost. This is also a good method for checking your own
takeoff.
Division 7 - Thermal & Moisture Protection
Roof Walkways
When estimating the installation of a membrane roof, be sure to
include the cost for walkway pavers to create a path to
roof-mounted mechanical equipment. You will more than likely be
required to install these in order to obtain a warranty.
Single Ply Roofing Sources
In many locations, manufacturers make their materials available
through one distributor/contractor franchise. If only one type
of roofing is specified, you may not have much choice as far as
acquiring costs or quotes.
Estimating the Specified System
Even though it may be less expensive to use a "suitable
substitute," the system that is specified is the one that should
be estimated. If you include as part of your estimate a
non-specified system and get the job, you may be required to
furnish the originally specified, more expensive roof system.
Sheet Metal Work
Do not assume that all sheet metal items are "off-the-shelf"
items. Gutters and downspouts as well as termite shields, gravel
stops, expansion joints, and reglets may need to be
shop-fabricated. Checking into information catalogs could save
quite a tidy sum in extras.
Interior Door Ratings
For walls to be considered fire-rated, any doors in those walls
must be fire-rated. Most plans do not spell out which interior
partitions are to be considered fire-rated. In commercial
applications, a rule of thumb is that all partitions that have
drywall (or masonry) from the floor to the above structure and
few, if any, penetrations should be considered fire-rated.
Door Schedule
If the drawings do not include a door schedule, it may be worth
the estimator's time to develop one, especially if the project
is large or complicated. On the schedule should be the opening
number, door type, size material, glass or louver requirements,
and remarks.
The door schedule should include a frame schedule listing the
frame material, type, and jamb, head and sill details.
Hardware requirements should be listed on the door schedule as
well. Keep in mind the fact that hardware can, in some
instances, be more costly than the door itself.
Handicap Access
While the drawings may not show it, local codes may require
special hardware and opening systems to allow a structure to be
accessible to the handicapped. Contact the local authorities for
their codes an requirements.
Special Doors
Special attention should be given to any oversized or unusual
type of doors. These items should not be priced on a prorated
basis, as they are generally special order items. The costs of
special doors can skyrocket, especially if they involve exotic
woods, special finishes, or special attention (which usually
means higher labor costs). Note also that special doors may
require a considerable amount of lead time for ordering and
shipping.
Window Schedule
As with all doors to be included in the project, all windows
should be listed on the drawings in a window schedule. If none
is included, it may be well worth the time to create one. The
schedule should contain the opening number, window type, window
size, glass type, frame material and details, and required
accessories and hardware.
Building Hardware
As a rule of thumb, building hardware for an average quality
building can be expected to run in the neighborhood of 2% of the
entire building cost.
General Note on Finishes
If, during the course of a project, the owner decides to cut
back on costs, this is not a good area in which to do it. When a
project is finished and the owner and prospective tenants walk
through, they will not be able to see a complicated foundation,
nor the marvelously engineered subsystems. What they will see
are the finishes. If the project is "cheapened" at this point,
it will show and dull the luster of an otherwise shining project.
Room Finish Schedule
A complete set of plans should contain a room finish schedule.
If one is not available, it would be well worth the time and
effort to put one together. A room finish schedule should
contain the room number, room name (for clarity), floor
materials, base materials, wainscot materials, wainscot height,
wall materials (for each wall), ceiling materials, and special
instructions. It is handy and easier to work out a room finish
schedule on a grid system.
Studs for Lathing and Plaster
If not specified, the studs for plaster partitions are usually
spaced at no greater than 16" on center.
Lathing Waste Factor
Allow a 5% waster factor when figuring the amount of lathing.
Plaster Allowances
Deductions for openings in plaster partitions vary by the
preference and experience of the estimator, from 0% for openings
of less than 2 S.F. to 50% for openings greater than 2 S.F.
For curved walls with a radius less than 6' allow twice as much
plaster.
Pricing a plaster and lath job depends on the quality of work
desired. A first class project will have variations in the wall
level of less than 1/16" in 10 feet. An ordinary plaster job (or
commercial grade) may have waves of 1/8" to 3/16" in 10 feet.
Overall, labor for first class work is approximately 20% higher
than ordinary or commercial grade work.
Drywall Deductions
A rule of thumb when estimating materials for drywall is to not
deduct for door or window openings of less than 32 square feet.
Wallcoverings
A single roll of wallpaper will cover approximately 36 S.F.
Allow approximately 6 S.F. per roll for waste. This means take
the total square foot area to be covered and divide by 30 to
determine the number of rolls needed.
For vinyls and grass cloth coverings with no patterns to match,
allow approximately 10% (3 square feet per roll) for waste. For
patterns requiring matching, allow up to 25% to 30%.
Waste can run as high as 50% to 60% for coverings with large,
bold, or intricate patterns.
Always specify wallcoverings from the same batch with identical
batch numbers. This will help to ensure that the colors and
patterns will match.
Surplus Finishes
Review the specifications to determine if there is any
requirement to provide certain amounts of extra floor tile,
ceiling pads, paint, wallcoverings, etc., for the owner's
maintenance department. In some cases, the owner may require a
substantial amount of materials, especially if it is a special
order or long lead time item.
Item Takeoff
When taking off Division 10 items, list each item called for,
along with the specified manufacturer. Often no substitutions
are allowed for specified Division 10 items.
Labor Cost for Installation
When receiving bids for Division 10 items, make sure that the
costs of installation are included. In many cases these items
are sold per unit without installation. If installation is not
included, inquire if delivery is included. Items sold by the
piece without installation usually do not include any shipping
costs.
Support Systems
Note that many Division 10 items require some type of support
system not usually supplied with the item -- such as support
brackets, plates or angles. These must be accounted for and may
need to be added to the appropriate division. Phrases in the
specifications that gloss over this subject and thus make it
difficult to recover any added costs include "The contractor
shall install all products in accordance with the manufacturers'
recommendations" and the like. Remember, it is much more costly
to install a behind-the-wall support system after the wall is in
place.
Preparation of Items
In some cases, Division 10 items may require some assembly
before installation. This assembly time can often exceed the
time required for installation.
Shop Smart
There can be a wide variance in costs for the exact same item.
Smart shopping for these items can help lower your overall bid.
Faulty Assumptions
Do not assume that items covered in Division 11 will be
purchased and installed by others outside of your contract. This
can be a costly error. Check all drawings for these items and
for terms such as "NIC" (Not In Contract) or "By Others." If
these or similar terms are not in evidence, then it is safe to
conclude that these are in your scope of work.
Installation of Items
In many cases Division 11 items are purchased by others, but
their installation is the contractor's responsibility. Check all
drawings and specifications carefully for these items.
Handling Charges
In cases where Division 11 items are purchased by others but
installed by the contractor, contractors often add a handling
charge. (10% of the estimated material costs is common
practice). This charge covers the receiving, handling, storage,
protection, and final delivery of these items.
Support Systems
Note that Division 11 items may require some type of support
system not usually supplied with the item -- such as support
brackets, plates, or angles. These need to be accounted for and
may need to be added to the appropriate division. Phrases in the
specifications that gloss over this subject an thus make it
difficult to recover any added costs include "The contractor
shall install all products in accordance with the manufacturers'
recommendations" and the like. Remember, it is much more costly
to install a behind-the-wall support system after the wall is in
place.
Preparation of Items
In some cases, Division 11 items may require assembly before
installation. Be aware that the assembly time can often exceed
the time required for installation.
Faulty Assumptions
Do not assume that items covered in Division 12 will be
purchased and installed outside of your contract, especially if
any furnishings or typical arrangements are shown on the
drawings. This could be costly assumption. Check all drawings
and specifications for these items and if any are found, check
for the terms "NIC" (Not In Contract) or "By Others." If these
or similar terms are not present, it is safe to conclude that
these items are in your scope of work.
Installation of Items
In many cases, Division 12 items are purchased by others, but
the contractor is responsible for them. Check all drawings and
specifications for these items.
Handling Charges
In cases where Division 12 items are purchased by others but are
to be installed by the contractor, many contractors add a
handling charge. (10% of the estimated material cost is common
practice.) This charge covers the receiving, handling, storage,
protection, and final delivery of these items.
Preparation of Items
In some cases, Division 12 items may require some assembly
before installation. The assembly time can often exceed the time
required for installation.
Cleaning Time
When installing materials purchased by others, be sure to allow
for cleaning time. Invariably, these items will need some
cleaning and this responsibility will fall upon the installer.
Division 13 - Special Construction
Covering All Bases
If you take outside quotes as an aid to estimating Division 13,
review the scope of work covered in those quotes. It may be that
the outside agent has wrongfully assumed that you will provide
traditionally supplied items such as excavation or an unloading
crane. Check to make sure that it is covered somewhere in your
estimate, and that it is not carried by both parties.
Interfaces
Review all documentation to ensure that all interfaces, such as
electrical connections and control wiring, are accounted for.
These items have a habit of falling through the cracks of an
estimate.
Elevator Doors
When preparing an estimate for elevators, check to make sure
that doors have been included, not only for the elevator itself,
but for each floor where the elevator stops.
Hydraulic Piston
When figuring the cost for a hydraulic elevator, make sure that
the excavation for the elevator piston is included in the
estimate. For each floor above grade that the elevator is to
travel, there should be an equal length of piston below grade.
Fire Stops
When estimating any vertical conveying system, make sure all
openings for doors, dumbwaiter access panels, etc., are
fire-rated per the applicable code. In case of a fire emergency,
their shaftways will otherwise act as a conduit for smoke and
heat.
Help
When in doubt about price, what is standard on elevators,
material selection, availability, etc., do not hesitate to call
on any of the elevator manufacturing companies directly. The
competition of your business can be fierce, and they will try to
assist you in any way they can.
Tie-in
Make sure that either the conveying system estimate, the
electrical estimate, or mechanical estimate include the tie-in
to the rest of the electrical and control systems. This is
another item that people often assume someone else has covered.
Plans and Specifications
Review all construction documentation before proceeding with the
estimate for Division 15. It is not unusual to find items on the
plans, but not in the specifications; or they may be in the
specifications but not on the drawings. Also check any and all
communications; the owner may have requested a change or
expressed a concern or a specific need, and not have had it
included in your drawings or specifications.
Review All Drawing Divisions
It is important to review all of the drawings available to
ensure that the systems called for will physically fit where
they are supposed to. For example, sometimes the architect
subcontracts out the HVAC design function as well as the
structural design. If the drawings are not carefully
coordinated, a conflict may result, such as inadequate space
under deep trusses where main ductwork was supposed to be
installed and a required finished ceiling height maintained.
Check Drawing Scales
When utilizing drawings from different sections of the plans,
always check to see if the drawing scales are the same. It has
happened that as estimator has ended up with twice the length of
piping needed (or worse, half) because he/she was not aware that
the drawing scales varied from structural to mechanical.
Document All Inconsistencies
All inconsistencies with standard practice, conflicts, omissions
and other concerns should be addressed before the final estimate
is resolved. Do not rely on memory which can become quickly
overloaded in a rush situation.
Temperature Control System
When estimating the cost of an HVAC system, check to see who is
responsible for providing and installing the temperature control
wiring system. In many cases, this item is overlooked, as it was
assumed that it would be included in the electrical estimate.
This can be a costly assumption.
Connecting to an Existing System
When tapping into an existing system for water, drainage or
waste, check with the local authorities (or building owner, in
the case of interior work) to see if it is required that they or
their designated contractor make the tap. Such surprises could
led to an unexpected expense or stoppage.
Non-Listed Items
It is important to include items that are not shown on the
plans, but must be priced. These items include, but are not
limited to, roof penetrations and pitchpots, dust protection,
coring floors and walls, temporary water supply, testing and
balancing HVAC systems, cleaning piping, purifying potable water
systems, clean-up, and final adjustments.
Cutting and Patching
Not all projects will be done under ideal conditions, that is,
wide open spaces with no interferences. Many times the
mechanical contractor will have to run duct or piping through
pre-existing partitions or partitions that have been recently
installed. Allowances must be made for cutting into the
partition ad the ensuing patching. Otherwise, a statement must
be included with the estimate that all cutting and patching will
be the responsibility of others.
Electrical Connections
Clarify who is responsible for connecting the electrical wiring
to mechanical items. It has been argued that the electrician is
responsible only for bringing the wiring to the unit, while
others maintain that it is the electrician's job to connect the
wiring.
Conduit
Conduit should be taken off in three main categories: power
distribution, branch power, and branch lighting. In this way,
all conduit does not have to be taken off in one session.
Instead the estimator can concentrate on systems and components,
thereby making it easier to ensure that all items have been
accounted for.
Aluminum Wiring
Remember that aluminum wiring of equal ampacity is larger in
diameter than copper and may require larger conduit.
Switchgear
When estimating the costs for the installation of switchgear,
especially large items, factors to review include access to the
site, access and setting at the installation site, required
connections, uncrating, pads, anchors, levelling, final assembly
of the components, and temporary protection from physical
damage, including from exposure to the environment.
Pads, Supports, and Panel Backing
While supports and pads may be shown on drawings for the larger
equipment, in many cases nothing is shown for smaller pieces
such as panelboards and area transformers. Whether a special
floor-to-ceiling support system is required, or just a piece of
plywood for the back of a panel, it must be included in the
costs.
Installation Equipment
Do not overlook the costs for equipment used in the installation
. If highlifts, scaffolding, or cherry pickers are available,
the field will use them in lieu of the proposed ladders.
Material Weights
The estimator should take the weights of materials into
consideration when completing a takeoff. Topics to consider
include: How will the materials be supported? What methods of
support are available? How high will the support structure have
to reach? Will the final support structure be able to withstand
the total burden? Is the support material included or separate
from the fixture/equipment/material specified?
Non-Listed Items
It is important to include items that are not documented in the
plans but must be priced. These items include, but are not
limited to, testing, equipment hookups, motor controls,
disconnect switches, special systems, dust protection, roof
penetrations, pitch pots for the roof, coring concrete floors
and walls, cleanup, and final adjustments.
Temporary Light and Power
Examine all contract documents to determine if providing
temporary power and lighting is included in your scope of work.
In many cases, temporary lighting and power requirements are not
specified in contract documents. Either way, you will probably
be required at some point to provide a cost for these items.
Depending on your bidding strategy, you may or may not want to
list this item as an alternate to your estimate. However, if it
is stated in the contract documents, then you will be fully
responsible for providing this service.
Cutting and Patching
Not all projects will be performed under ideal conditions--that
is, wide open spaces with no interferences. Many times the
electrical contractor will have to run conduit through
pre-existing partitions or partitions that were recently
installed. Allowances must be made for this cutting into the
partition and the ensuing patching. Otherwise a statement must
be included with the estimate that all cutting and patching will
be the responsibility of others.
Mechanical Connections
Clarify who is responsible for the connecting of the electrical
wiring to mechanical items. It has been argued that the
electrician is responsible only for bringing the wiring to the
unit, while others say it is the electrician's job to connect
the wiring.
Fixture and Device Counts
Performing a fixture takeoff is a good way to become familiar
with a proposed project. Fixtures should be taken off
room-by-room, using the fixture schedule (if provided),
specifications, and the ceiling plan. While performing the
count, it is a good idea to also take off the controlling
devices and add accessories (plaster rings, outlet boxes, cover
plates, etc.). A spreadsheet works well for this purpose.
When finished, this takeoff can be used for purchasing,
accounting and billing, and cost control.
Special Systems
When estimating material costs for special systems, it is always
prudent to obtain manufacturers' quotes for equipment prices.
Also, some installations will require special accessories.
Often, the sales engineers are a good source of information on
these requirements.
|